Anto01 9ab5b3c9d8 docs(planning): V1 Completion Plan — Codex sign-off (third round)
Codex's third-round audit closed the remaining five open questions
with concrete file:line resolutions, patched inline in the plan:

- F-7 (P1): graduation stack is partially built — graduated_to_entity_id
  at database.py:143-146, graduated memory status, promote preserves
  original at service.py:354-356, tests at test_engineering_v1_phase5.py.
  Gaps: missing direct POST /memory/{id}/graduate route; spec's
  knowledge -> Fact mismatches ontology (no fact type). Reconcile to
  parameter or similar. V1-E 2 days -> 3-4 days.

- Q-5 / V1-D (P2): renderer reads wall-clock in _footer at mirror.py:320.
  Fix is injecting regenerated timestamp + checksum as renderer inputs,
  sorting DB iteration, removing dict ordering deps. Render code must
  not call wall-clock directly.

- project vs project_id (P3): doc note only, no storage rename.

- Total estimate: 17.5-19.5 focused days (calendar buffer on top).

- Release notes must NOT canonize "Minions" as a V2 name. Use neutral
  "queued background processing / async workers" wording.

Sign-off from Codex: "with those edits, I'd sign off on the five
questions. The only non-architectural uncertainty left in the plan is
scheduling discipline against the current Now list; that does not
block V1-0 once the soak window and memory-density gate clear."

Plan frozen. V1-0 starts after pipeline soak (~2026-04-26) and the
100-active-memory density gate clear.

Co-Authored-By: Codex <noreply@anthropic.com>
Co-Authored-By: Claude Opus 4.7 (1M context) <noreply@anthropic.com>
2026-04-22 14:24:43 -04:00
..