# Project Status Dashboard Updated: 2026-04-02 04:00 AM (Nightly Digestion OP_11) ## Active Projects ### πŸ”­ GigaBIT M1 β€” Reference Frame Stiffness Characterization - **Phase:** Active β€” Model Setup - **Client:** StarSpec (Adyn Miles) - **Project ID:** P04-GigaBIT-M1 - **Created:** 2026-03-04 - **Objective:** Determine minimum stiffness requirements for StarSpec's reference frame at 5 mirror support interface points. Quantify WFE sensitivity to frame compliance. - **Method:** Hybrid B+D (sensitivity + stiffness sweep), SOL 101, ~42 runs total - **Key numbers:** Ξ”WFE budget ≀1.0 nm RMS, system allocation ≀22 nm RMS (contract), mechanical target <14 nm RMS - **Location:** `/home/papa/repos/Atomizer/projects/gigabit-m1-frame-stiffness/` - **PKM:** `/home/papa/obsidian-vault/2-Projects/P04-GigaBIT-M1/` - **Owner:** Antoine (direct) ### βœ… P-Zernike-Validation (GigaBIT M1 Risk Reduction) - **Phase:** βœ… COMPLETE (2026-03-09) - **What:** Zernike pipeline V&V β€” 18 test cases pass, cross-validated against prysm v0.21.1 to machine precision (<1e-13 nm) - **Commits:** `f9373be` (round-trip validation), `075ad36` (prysm cross-validation + report figures) - **Requested by:** Adyn Miles (StarSpec) for risk reduction before M2/M3 ordering - **Owner:** Antoine (direct) ### πŸ”© Hydrotech Beam β€” Optimization - **Phase:** DOE Phase 1 complete, awaiting Phase 2 (TPE) - **Status:** ⏸️ BLOCKED β€” Mass NaN fix committed (580ed65), needs pull + test on dalidou - **Key numbers:** 39/51 trials solved, 0 fully feasible (displacement), constraint relaxed to 20mm - **Next:** Antoine pulls fix on dalidou β†’ test single trial β†’ rerun DOE β†’ Phase 2 TPE - **Note:** Lower priority β€” Antoine focused on GigaBIT M1 work - **Owner:** Tech Lead + Study Builder ### πŸ“ Atomizer Project Standard - **Phase:** Review complete, awaiting CEO decision - **Status:** 🟑 AWAITING APPROVAL - **Deliverables ready:** Full spec, tech-lead review, auditor audit, secretary synthesis - **Location:** `/home/papa/atomizer/workspaces/shared/standardization/` - **Key decision:** Auditor recommends MVS (minimal viable standard) over full spec. Antoine to decide. - **Owner:** Manager ### πŸ”Ί Adaptive Isogrid Plate Lightweighting - **Phase:** Technical spec locked, reviews complete - **Status:** 🟑 AWAITING CEO REVIEW - **Deliverables ready:** Full technical spec (32KB), optimizer review, tech-lead review, webster review - **Location:** `/home/papa/atomizer/workspaces/shared/war-room-isogrid/` - **Next:** CEO review β†’ implementation planning - **Owner:** Manager / Tech Lead ### πŸ“¦ Atomizer V2 Migration - **Phase:** βœ… COMPLETE (2026-02-23) - **Post-migration:** V1 tagged `v1-final`, kept active. AOMβ†’Obsidian auto-sync via crontab. Phase 6 (archive V1) deferred until Antoine switches production work. - **Remaining roadmap:** Items 4-9 in ROADMAP-NEXT.md ### 🏒 Atomizer/HQ Separation - **Phase:** βœ… COMPLETE (2026-02-23) - **Decision:** DEC-037 ## Infrastructure Updates - **Tier 2 dev workflow** added (2026-03-07, commit `b3162aa`): Windows test runner (`run_tests.bat`), result sync via Syncthing, JSON result capture, `--quick` mode for NX-independent tests - **Daily HQ syncs** continue (automated commits through Mar 12) ## Outstanding Blockers - **3 projects** awaiting CEO input (Hydrotech, Project Standard, Isogrid) β€” deprioritized while Antoine focuses on GigaBIT M1 - No newly verified infrastructure blockers during this digestion pass; prior Webster search-tool/API-key issue appears historical and should only be reinstated if it reproduces ## Mission Control β€” Stale Tasks Several MC tasks have been in `in_progress` or `review` since mid-February with no updates: - ATZ-2f1634: P-Adaptive-Isogrid (in_progress) - ATZ-74f02a: Atomizer Overhaul (in_progress) - ATZ-839392: Project Standard β€” Introspection (in_progress) - ATZ-749aac, ATZ-d3fce9, ATZ-05c017, ATZ-21695d: all in review These should be resolved (completed or closed) when Antoine returns to HQ work.