Nightly Digestion — OP_11 (Incremental)

STORE

  • V2 Migration marked COMPLETE in MEMORY.md (already done Feb 23). Coherence audit (conditional pass) + preflight fixes (3 critical issues resolved) captured in shared/reviews/. HQ Separation complete (DEC-037).
  • No new CEO corrections to process.
  • No new project activity since Feb 23 afternoon — team quiet (weekend/waiting on CEO decisions).

DISCARD

  • Memory files Feb 8 + Feb 9 are 16 days old — within 30-day retention, no pruning needed yet.
  • No contradictions found. MEMORY.md Active Projects section is current and accurate.
  • Sub-agent spawning blocker from Feb 22: appeared to self-resolve (auditor spawned successfully that same day). Downgrading from blocker to intermittent issue.

SORT

  • Coherence audit + preflight fixes correctly placed in shared/reviews/ (project-level).
  • No session-level patterns to promote.

REPAIR

  • PROJECT_STATUS.md was stale — still showed V2 Migration as "AWAITING CEO DECISIONS" when it's actually COMPLETE. Updated to reflect V2 completion, HQ separation, coherence audit delivery, and correct blocker ages.
  • Auditor P-Adaptive-Isogrid block: now 9 days. This is becoming chronic — may need Manager intervention to unblock (assign directly or close).
  • Webster web_search API key: 5 days waiting on Mario. Still unresolved.

EVOLVE

  • Observation: Team is in a holding pattern — 3 projects awaiting CEO input (Project Standard, Isogrid, Hydrotech). No productive work can proceed on these without Antoine. When he returns, priority triage is essential.
  • Observation: The Auditor blocker (9 days) suggests the async challenge-in-channel approach isn't working for Tech Lead. Consider direct task assignment via sessions_spawn next time.
  • No process changes needed.

SELF-DOCUMENT

  • PROJECT_STATUS.md updated (was stale, now current).
  • MEMORY.md already current from Feb 23 session.