Project Status Dashboard

Updated: 2026-03-03 04:00 AM (Nightly Digestion OP_11)

Active Projects

📦 Atomizer V2 Migration

  • Phase: COMPLETE (2026-02-23)
  • What happened: 8 commits pushed to Gitea. 218+ Python files, 58 tests passing. All phases done: repo bootstrap, core engine port, integration testing, reference implementation, CLAUDE.md, Data Contracts (5 dataclasses), Pipeline-NX integration tests. Dalidou validated: import atomizer v2.0.0 + 24/24 tests on Windows.
  • Post-migration: Coherence audit delivered (conditional pass, 3 critical findings fixed in preflight). V1 tagged v1-final, kept active for current optimizations. AOM→Obsidian auto-sync via crontab. Phase 6 (archive V1) deferred until Antoine switches production work.
  • Remaining roadmap: Items 4-9 in ROADMAP-NEXT.md (docs/dev/)
  • Location: 192.168.86.50:3000/Antoine/Atomizer-V2, Obsidian vault P-Atomizer-Operating-Manual/
  • Owner: Manager

🏢 Atomizer/HQ Separation

  • Phase: COMPLETE (2026-02-23)
  • Decision: DEC-037 — Atomizer = product (V2 repo), HQ = AI operations team (HQ repo). AOM governs the product. 7 AOM docs updated. HQ repo pushed to Gitea (218 files).
  • Owner: Manager

🔩 Hydrotech Beam — Optimization

  • Phase: DOE Phase 1 complete, awaiting Phase 2 (TPE)
  • Status: ⏸️ BLOCKED — Mass NaN fix committed (580ed65), needs pull + test on dalidou
  • Key numbers: 39/51 trials solved, 0 fully feasible (displacement), constraint relaxed to 20mm
  • Next: Antoine pulls fix on dalidou → test single trial → rerun DOE → Phase 2 TPE
  • Owner: Tech Lead + Study Builder

📐 Atomizer Project Standard

  • Phase: Review complete, awaiting CEO decision
  • Status: 🟡 AWAITING APPROVAL
  • Deliverables ready: Full spec, tech-lead review, auditor audit, secretary synthesis
  • Location: shared/standardization/
  • Key decision: Auditor recommends MVS (minimal viable standard) over full spec. Antoine to decide.
  • Owner: Manager

🔺 Adaptive Isogrid Plate Lightweighting

  • Phase: Technical spec locked, reviews complete
  • Status: 🟡 AWAITING CEO REVIEW
  • Deliverables ready: Full technical spec (32KB), optimizer review, tech-lead review, webster review
  • Location: shared/war-room-isogrid/
  • Next: CEO review → implementation planning
  • Owner: Manager / Tech Lead

🔬 Material Research (M2 Mirror Trade Study)

  • Phase: Research complete
  • Status: Data collected (Zerodur, Clearceram-Z HS, Invar 36, SiC)
  • Next: Awaiting project context to produce recommendation
  • Owner: Webster

Outstanding Blockers

  • Auditor blocked on P-Adaptive-Isogrid review since Feb 16 (11 days — chronic, moot until CEO reviews Isogrid; closing next active session)
  • Webster web_search API key missing (needs Mario, since Feb 19 — 8 days)
  • 3 projects simultaneously awaiting CEO input — triage needed when Antoine returns

Recent Activity

  • 2026-02-24: Arsenal Development Plan — Tech Lead produced dev blueprint (multi-solver expansion, 6-sprint roadmap). Auditor delivered risk analysis + quality gates (flagged 5 simultaneous problem streams, recommended phased de-risking). Good team output.
  • 2026-02-23: V2 Migration COMPLETE (8 commits, 218+ files, 58 tests). HQ Separation COMPLETE (DEC-037). Coherence audit + preflight fixes delivered.
  • 2026-02-22: AOM 100% complete (48 docs), tool-agnostic architecture
  • 2026-02-18: Project standardization package assembled and reviewed